🔵 نمونه سوال آمادگی برای آزمون PMP و CAPM:
You are the Project Manager assigned to build a next generation vehicle. You identify a dependency that the wheels must be designed and developed before the assembly of the vehicle can be performed. This is an example of which type of dependency?
▪️ A. External
▫️ B. Discretionary
▪️ C. Soft logic
▫️ D. Mandatory